From the M25 team:
Ladies and Gentlemen
We are nearing the completion of widening works on the anticlockwise carriageway and are now
making changes to the traffic management in readiness to switch to working on the clockwise
carriageway. Below is the programme detailing these changes.
M25 Widening Junction 27-30
Traffic management switch from anticlockwise to clockwise carriageway
- 8th, 9th December overnight on clockwise carriageway between Junction 28 and 29 - removal of varioguard
- 10th, 11th December overnight on anticlockwise carriageway between Junction 28 and 29 - installation of varioguard for new contraflow lane
- 12th December overnight - traffic on anticlockwise carriageway moved out of contraflow
- 12th December overnight - traffic on clockwise carriageway moved into contraflow lane
- 13th December for 5/6 nights - installation of varioguard on clockwise carriageway lane 1
Best regds
Suzy Keeley
Customer Relations Manager
Skanska Balfour Beatty Joint Venture
Codham Hall
Brentwood
Essex
CM13 3FB